Construction process Casa Milà
la casa milà being built
in 1905, milà , segimón married , on june 9, roser segimón bought house garden occupied area of 1,835 square meters, located on paseo de gracia, 92. in september, commissioned gaudí building them new house idea of living in main floor , renting out rest of apartments. on february 2, 1906, project presented barcelona city council , works began, demolishing pre-existing building instead of reforming it, in case of casa batlló.
the building completed in december 1910 , owner asked gaudí make certificate inhabit main floor, city council authorized in october 1911, , couple moved in. on october 31, 1912, gaudí issued certificate stating that, in accordance plans , direction, work had been completed , whole house ready rented.